Pleasant Community 1 (037-00516)
Pleasant Community 1 was spudded on September 3, 1949 by the Rothschild Oil Company, and completed on September 12, 1949. The total depth was 1731 feet. This well never produced. It was converted to a waste water injection well in 1955. That was ended sometime in the 1980's.

Rig on site. (11/30/2022)

Another view. (11/30/2022)

Closeup of wellhead. Whatever work that the rig was doing is complete. Probably cleaning out the well bore was done. (12/3/2022)

Rig is back at Pleasant Community. More work was evidently needed in the well bore. The well below Pleasant Community in the red circle is Fehsel 2. The well circled in the below right of the image is Fee 6. (12/21/2022)

The rig was moved to Fehsel 2. Pleasant Community is in the foreground. (12/25/2022)

Here is the Pleasant Community wellhead again. There also used to be an oil tank at this site. Hardward for the tank is visible near the trash bin. It will eventually be removed during the site clean-up. (12/25/2022)

Finally, they are almost done. The cement work is completed and a hole has been dug in preparation of the casing being cut off about five feet below the surface. (1/28/2023)

The casing has been cutoff below the surface. There will be a steel plate with the well number welded somewhere on the casing, probably right on top. (2/2/2023)

Abandonment completed. Site restored to a "natural" condition. (5/21/2023)